Hydroelectric projects
| Name of the Project | Installed Capacity MW |
Energy Potential MU |
Major Works Started in |
Original Estimate in Rs. lakhs |
Latest Estimate in Rs. lakhs |
Remarks |
| Azhutha Diversion, Idukki | 57 | 1987 | 290 | 1446 | Partially Commissioned | |
| Kuttiadi Tail Race, Kozhikode | 3.75 | 17.10 | 1989 | 397 | 1494 | Commissioned. |
| Vazhikkadavu Diversion, Idukki | 24 | 1989 | 186 | 1599 | Commissioned. | |
| Kuttiadi Additional Extension | 100 | 240.5 | 2000 | 6200 | 22050 | Commissioned. |
| Bhoothathankettu, Ernakulam | 16 | 61.5 | 1994 | 3283 |
Private Sector |
|
| Ullungal | 7 | 34 | Private Sector | |||
| Karikkayam | 15 | 72.7 | 1994 | 3860 | Private Sector |
|
| Kuttiyar Diversion | 37 | 1991 | 214 | 2900 |
Commissioned |
|
| Sengulam Augmentation | 85 | 2001 | 4763 | 5000 | To be completed in 2013 | |
| Thottiyar | 40 |
99 |
13679 |
20704 |
To be completed in 2012 | |
| Athirappally | 163 | 386 | 2001 | 10254 |
31590 |
MoEF withdraws clearance |
| Vadakkepuzha Diversion | 12 | 131 |
514 | Commissioned | ||
| Neriamangalam Extension | 25 | 58.27 |
2003 | 3506 | 4776 | Commissioned |
| Sengulam Tail Race | 3.60 |
12.57 |
To be completed in 2011 | |||
| Mankulam | 40 | 82 | To be completed in 2011 | |||
| Pallivasal Extension | 60 | 164.87 |
2007 |
17500 |
31000 |
To be completed in 2012 |
| Adayanpara |
3.5 |
9.01 |
2007 |
2132 |
2132 | To be completed in 2010 |
| Barapol I & II |
25 | 60 | To be completed in 2011 |
|||
| Chalippuzha | 90 | Project Report ready | ||||
| Thoovalar | 4 | Project Report ready | ||||
| Alamparathodu | 3 | Project Report ready | ||||
| Sabarigiri Additional Capacity | 35 | 154.51 | 94.64 | Renovation of Sabarigiri Project | ||
| Kakkadam Poyil 1 | 20 | 55 |
||||
| Kakkadam Poyil 2 |
5 |
11 |
To be completed in 2011 | |||
| Anackam Poyil |
7.50 |
22.63 |
On the drawing board | |||
| Kandappanchal |
5 |
On the drawing board | ||||
| Pathamkayom |
4 |
On the drawing board | ||||
| Olickal |
4.5 |
10.18 |
28.09 |
On the drawing board | ||
| Chathankottu Nada 2 |
6 |
14.76 |
To be completed in 2010 | |||
| Vilangadu |
7.5 |
22.63 |
To be completed in 2010 | |||
| Maniyar Tail Race |
4 |
16 |
To be completed in 2010 | |||
| Perunthenaruvi |
10 |
25.77 |
To be completed in 2010 | |||
| Marumala |
5 |
On the drawing board | ||||
| Pathrakadavu, Silent Valley | 70 | 214 | 24706 | Controversial EIA, as good as abandoned |
||
| Poozhithodu |
4.80 |
10.97 |
2009 |
2949 |
3950 |
To be completed in 2010 |
| Achankovil |
30 |
75.80 |
To be completed in 2011 | |||
| Chinnar |
24 |
78 |
To be completed in 2011 | |||
| Perunthenaruvi |
6 |
25.77 |
To be completed in 2010 | |||
| Chembukadavu III |
6 |
14.92 |
53.53 |
On the drawing board | ||
| Poovarathodu |
2.7 |
5.88 |
20.46 |
On the drawing board | ||
| Koodam |
4.5 |
10.5 |
37.59 |
On the drawing board | ||
| Poringalkuthu |
24 |
Cabinet clearance received |
Thermal Projects (Private Sector)
| Name of the Project | Installed Capacity MW | Energy Potential (MU) |
Remarks |
| DCP, Kasaragod | 105 | 749 |
Work under way |
| Kannur Power Corporation | 513 | Work to be started | |
| SASIN, Kochi | 679 | Work to be started | |
| Cochin Refineries, Ambalamugal | 621 | Joint Sector |
Besides the above, the State Electricity Board is planning some mini hydroelectric schemes such as Chimony (2.5 MW), Peechi (1.50 MW) and Pasukadavu (2 MW). Some small hydroelectric units are being constructed with Chinese collaboration. Besides, 62 small projects are proposed for private investment. Palakkad district panchayat is implementing Meenvallom project (2.4 MW).
The State E;lectricity Board proposes to
complete 34 small projects including Neriamangalam extension and
Kuttiyadi tail race before 2011. They will add installed capacity of
about 200 MW (558.819 MU). 5MW wind farm at Ramackalmedu (5 MW, 15 MU)
is proposed to be taken up during the current Plan period.
| HOME | Kerala Power System at a Glance | Hydropotential of Kerala |